Perfect Welding

The current page does not exist in the target language.

Do you want to change the language and go to the home page or do you want to stay on the current page?

Change Language
Perfect Welding
Bilfinger worker

Bilfinger Industrial Services Austria Strong Partner for the industry

The operating companies Bilfinger VAM and Bilfinger Chemserv as well as Bilfinger Shared Services were merged into Bilfinger Industrial Services GmbH.

Bilfinger Industrial Services Austria is now the largest industrial service provider in Austria with headquarters located in Linz and 9 further locations in Austria as well as in the neighbouring countries.

What's your welding challenge?

BILFINGER INDUSTRIAL SERVICES AUSTRIA

Company Headquarters:
Linz

Sites:
9 locations in Austria as well as in the neighbouring countries

Employees:
approximately 2.000

Manufactures:
Industrial service providers
National and international project business
Engineering services

Fronius Product Used:
TPS 500i with an eight-meter-long PullMig welding torch (MHP 320i PM W / MHP 280i PM G)

Processes Used:
PMC pulse process Fillet welds and some V butt welds with a total length of roughly 600 meters

Portrait

» The extended operating radius due to the long hosepack allowed us to forgo the second manhole for each segment, saving us all the additional work this involved. Meanwhile, the power source could be placed outside the gate body together with the wirefeeder. This not only gives the welder better freedom of movement, but also facilitates access and recovery for emergency rescue workers, which is crucial for us. «

Bernhard Brindl, Project Manager in the Hydro Business department at the Bilfinger Industrial Services site

Requests

Fish belly flaps
Construction from steel components for the Traunleiten hydroelectric power plant, which is undergoing significant reconstruction works. The contract covers the engineering, production, delivery, and assembly of 23 different steel components weighing around 350 tons in total, including intake gates, turbine intake bulkhead gates, coarse screens to protect the turbines, and two weir gates (fish belly flap gates). The gate bodies were divided into three segments, with the longest measuring in at around 16 meters. With a segment length of 16 meters, at least two of these access points would be required to allow for welding tasks to be taken care of inside the gate body with the equipment previously available. Welders would have needed to take the power source, including the wirefeeder, inside the workpiece in order to achieve all the necessary welding positions.

Solution

Welding machine with large hose package
An eight-meter-long PullMig welding torch (MHP 320i PM W/MHP 280i PM G) with a TPS 500i. The extended operating radius due to the long hosepack allowed to forgo the second manhole for each segment, saving all the additional work this involved. Because every additional manhole represents a potential weak point where water could penetrate.

Fronius Product in use



Let's get connected!

Send your non-binding request directly to Fronius

Let’s get connected.

    Thank you for your message. We will process your request as soon as possible.

    Caffee, glasses, keyboard and newsletter

    Register for the International Newsletter!

    Stay up-to-date and immerse yourself in the world of Fronius Perfect Welding with Weld Informed.